Whats' Longxiang Mold Delivery time?
- Share
- Issue Time
- Jan 2,2018
In general
1-2 days for DFMEA report
2-3 days for mold design and making mold drawing
25-40 days for mold making.
In general
1-2 days for DFMEA report
2-3 days for mold design and making mold drawing
25-40 days for mold making.